The South Yorkshire Mayoral Combined Authority (SYMCA) has issued a statement after the lease between the City of Doncaster Council and Peel Land allowing the reopening of Doncaster Sheffield Airport was leaked.
Details of a secret termination clause in the lease, first reported by the Yorkshire Post and later verified by the Local Democracy Reporting Service (LDRS), revealed Peel could terminate the lease if planning permission was not granted for a number of planning applications the company would make near the airport site.
The leak caused outrage at a City of Doncaster Council meeting on Thursday, January 22, 2026, with councillors demanding answers on why this clause was never revealed to elected members when they were asked to approve a £57million loan in November 2025, which was understood to be do-or-die for the reopening project.
Now, following enquiries from the LDRS, the SYMCA, who approved nearly £160m in public money for the reopening after an extensive assurance process of its own, have issued a statement regarding the contents of the leaked lease.


An SYMCA spokesperson said: “SYMCA has worked with City of Doncaster Council (CDC) since the closure of DSA to bring an airport back to South Yorkshire to deliver jobs and opportunities to our communities.
“In September last year conditional approval of £159.52m was given to support the reopening of the airport.
“As was made clear in reports that went to September’s SYMCA board, the release of this funding is subject to meeting conditions designed to mitigate the risks highlighted in those board reports, including those related to the superior headlease.
“Work to meet these conditions has continued since, with positive progress made. Satisfactory completion of them remains a condition of funding being released.
“We continue to work with CDC to deliver the benefits a re‑opened DSA can deliver for communities across South Yorkshire.”
The planning applications referred to in the termination clauses were approved in November 2025. They included plans for 1,200 homes or 1,400 homes on a site next to DSA.
Representatives for the Peel Group said in the planning committee meetings that they would be acting on the 1,400 home application if both were approved.
Members of the planning committee, which is made up of Reform UK, Labour and Conservative councillors, have informed the LDRS they were not aware of the termination clause in the lease during the meeting.
Planning officials informed the committee panel the applications from Peel were fully acceptable under planning law and there is no suggestion that the applications were wrongfully given approval.
“That clause did not guarantee that they would receive planning permission and should not be read as though it does.”
During the full council meeting following the leak on January 22, 2026, Mayor Ros Jones insisted in a statement that “that clause did not guarantee that they would receive planning permission and should not be read as though it does”.
Mayor Jones also revealed she was working with the council’s monitoring officer, Scott Fawcus, on a way to share the commercially sensitive lease with elected members, whilst ensuring it remains confidential and is not shared outside of those individuals.
She refused to resign and refuted claims from Reform UK councillors she had mislead the public and later added: “This Council enters into contracts and agreements with many businesses and a guiding principle of those arrangements is that they must be dealt with in a commercial confidential manner.


“Planning is a quasi-judicial process, that as the Directly Elected Mayor I cannot get involved with. However, to reiterate every planning application has to be determined on its own merits and by the Planning Committee.
“The role of (the) planning committee is to carry out impartial decision-making on development, focusing on planning merits, not politics, as elected councillors who weigh planning policies, officer recommendations and public input, whether that be objections and or support, Planning Committee then have to vote to either approve or refuse developments.”
During an hour for questions from councillors, Mayor Jones claimed, misleadingly, that the details for the termination clauses had been public “for many years”.
The Mayor was referring to a March 2024 decision document on the council website to accept the lease with Peel, which makes no reference to planning permission-linked termination clauses specifically.
Instead, it reads: “Section 8, of the lease (Option to Determine) contains a section on break clauses and the factors which could trigger the landlord to terminate the lease.
“CDC will need to actively manage the business arrangement associated with the Airport site to minimise these risks.”
A spokesperson for Doncaster Council said: “Whilst we do not comment on apparently leaked documents, what we will say in general is that any clauses in a lease or legal document are advised upon by our legal representatives and follow due diligence.
“Planning matters are governed by and overseen by a quasi-judicial committee which will determine any planning applications on planning law and separate to any other council business. Planning applications are discussed on their individual merits and subject to scrutiny at several levels.”