Deputy mayor blames 'unforeseeable complications' as cost of Doncaster flooding scheme quadruples
The cost to implement the Doncaster Road surface water scheme reached a quarter of a million pounds.
The deputy mayor of Doncaster has blamed “unforeseeable complications” after the cost to implement a road safety scheme at a flooding hotspot nearly quadrupled compared to initial estimates.
In April 2026, the City of Doncaster Council’s service director for finance and technology, Faye Tyas, approved an additional £181,000 for a surface water scheme on Doncaster Road in High Melton.
It brought the total cost of the scheme to £250,000, nearly four times the initial £69,000 estimate.
Councillor Glyn Jones, the deputy mayor of Doncaster and cabinet member for environment, housing and safer communities, said: “While extensive preparation went into the project before it went ahead, unforeseeable complications arose related to environmental conditions and other restrictions.


“Overcoming these issues required our teams to source specialist equipment and machinery and to adjust their construction methods, which is why additional funding was needed.”
According to the decision papers, Doncaster Road is a “high-risk location” for flooding and current reactive methods to addressing surface water at the site represent “an inefficient use of a critical asset”.
These methods include jetting tankers which travel around the borough removing water from affected areas, which require road closures as the tankers operate.
As an alternative, the decision was taken to implement a new sustainable drainage system (SuDS) at the site, which mimics natural drainage.
Cllr Jones said: “This scheme provides a long-term solution to a problem that has made part of our road network historically susceptible to flooding and unplanned closures. Going forward, it is expected to improve road safety in Doncaster, reduce ongoing disruption for motorists, and generally help keep people moving throughout our city.
“Now that the scheme is complete, we look forward to the people of Doncaster being able to travel around our city with less disruption.”
The decision document states the original estimate “did not adequately account for the complications associated with the project’s scale and timeline”.
It reads: “A significant portion of the cost overrun can be linked to the original, unsustainable budget because of unforeseen geological conditions, increasing time constraints, and labour and material escalation allowances.
“The estimates were prepared using trial hole data, which did not clearly indicate the depth of rock requiring excavation. Had this information been available, a more accurate estimate could have been provided.”
The report also stated that the costings involved in the project, including the £181,000 of extra funds, were “sensitive” and not to be published.
It meant the figures were redacted in the decision papers, however, a description of the decision on the council website had not censored the totals and disclosed the figures.