Doncaster-Scunthorpe train services resume after landslip disruption
and live on Freeview channel 276
The line has been closed since Thursday to allow vital repairs to take place following a landslip on June 12. Initially, the line was able to remain open to a reduced service with Network Rail teams on site monitoring the area.
However, as these services had to travel at a significantly reduced speed, Network Rail took the decision to close the railway for seven days to carry out repairs.S
Advertisement
Hide AdAdvertisement
Hide AdSteel piles installed to stabilise the embankment were scheduled to take seven days, however good progress on site has meant that the repairs were completed earlier than planned allowing a full train service to resume today.
During the closure, there has been a rail replacement service between Doncaster and Scunthorpe to keep those who must travel moving.
Passengers are reminded that they should continue to avoid public transport where possible. Those who do need to travel on public transport should wear face coverings to protect themselves and others, however, some passengers are exempt, including young children, people with hidden disabilities and those with breathing difficulties.
Matt Rice, Route Director for Network Rail’s North and East Route, said: “Closing a portion of the railway is never an easy decision to make, which is why we are delighted that the line between Scunthorpe and Doncaster can reopen earlier than planned.
“We’d like to thank all those who have been impacted by this incident for their patience whilst these vital repairs were carried out.”