Biggest upgrade of East Coast Main Line - which travels through Doncaster - will see the first major closure of the route in 20 years

The biggest upgrade of the East Coast Main Line in a generation will see the first major closure of the route in 20 years this summer.
The East Coast upgradeThe East Coast upgrade
The East Coast upgrade

The £1.2bn upgrade plan is set to create capacity for up to 10,000 extra seats a day on long-distance services, see faster journeys and improve reliability for passengers.

Early route improvement work has already taken place, but the first major engineering upgrade will mean no trains are able to travel between Peterborough or Cambridge and London King’s Cross or London St Pancras International during the August Bank Holiday weekend.

The East Coast upgradeThe East Coast upgrade
The East Coast upgrade
Read More
£10.65M for link road from M18 to Doncaster West Moor Park East site which will ...
Hide Ad
Hide Ad

“We know this work will have an impact on people who use the line – we’re doing everything we can to keep disruption to a minimum, but passengers will need to plan ahead and check before they travel.

“Once completed, this upgrade will improve journeys and ensure we can continue to provide a service which meets the needs of the passengers, communities and economies we serve.”

Once complete, the improvements will mean additional services for passengers travelling on the route, improving choice and reducing congestion for travellers. The work will also reduce journey times, meaning passengers can spend less time on the train and more time with friends and family.

The engineering projects along the line will bring increased reliability and fewer delays for all passengers, including the hundreds of thousands of passengers who use the line to commute into the capital.

Hide Ad
Hide Ad

As well as the August Bank Holiday closure, there will be a slightly reduced service on the weekend of 13/14 July for work to be carried out to remove signalling equipment from a disused railway tunnel ahead of laying new track. It will eventually increase the number of tracks into King’s Cross station from four to six.

Over the Bank Holiday Weekend, major work is taking place between Peterborough and London King’s Cross, as well as a track renewal in Newark. Passengers using services which start or terminate in the capital are strongly advised not to travel on 24/25 August and to instead travel on Friday, 23 or Tuesday, 27. Work at Newark will continue on Monday, 26 August which means a reduced train service will run.

Passengers can see how their journey will be affected by visiting http://eastcoastupgrade.co.uk/. The rail industry is working together to keep passenger disruption to a minimum by carrying out work at multiple locations along the route at the same time.

“New trains are going into service on the route, and new trains need new infrastructure. This is essential work that will allow more trains to run and provide quicker journeys on long-distance services.”